Practical compliance with concrete standards
It can be seen that although designing a trial mix to meet a given grade can be done within a reasonable […]
It can be seen that although designing a trial mix to meet a given grade can be done within a reasonable […]
In the past, most survey work depended on triangulation from known fixed points using a theodolite and this may still be
Photographic records of the project can be invaluable and their cost is small relative to their worth. The following list
When the contractor assesses the amount of filling he will need to transport to achieve a given earthwork construction, he has
Arrangements for payment under design, build and operate (DBO) contracts may be partly direct and partly by income derived from
Payment under design, build and operate contracts Read Post »
Most standard conditions of contract contain specific provisions for interim payments and require payment of interest to the contractor if
Unless there is some stipulation that a lump sum is to be paid in stages it only becomes payable when the
Payment of lump sums, method related items and any adjustment item Read Post »
The ICE conditions and similar permit payment to be made to cover part of the cost to the contractor of materials
Aproblem arising with Clause 12 claims is assessing the cost of overcoming the unforeseen conditions. When the contractor has notified a