Agreeing quantities for payment

The way in which the resident engineer should measure quantities has already been described in Section 13.6. In that section the importance was emphasized of making clear what has been measured, and what has been agreed for payment with sketches as necessary.
It is strongly advisable that the resident engineer should take the lead in assessing final quantities. He or a member of his staff should supply quantity calculations to the contractor (or his quantity surveyors) and request agreement.
If the opposite method is adopted of the contractor supplying his quantity calculations for the resident engineer to check, the resident engineer may find it difficult or impossible to find out why some contractors quantities differ from his own. This is especially so if the contractors quantity calculations  are done according to some computer package which is unfamiliar to the resident engineer, or if no sketches are provided by the contractor to explain how his quantity has been calculated.

Some items will need measurement in the field, such as trench depths for pipelines, excavation and mass concrete to foundations, etc. This may be done by the resident engineers inspector who agrees the measurement with the appropriate foreman, a written advice note being sent immediately to the contractor giving the agreed figures. Sometimes joint measurement is arranged.
Other quantities can be taken from drawings if no variation has occurred.
Where an item of work is only partly done, a rough estimate of the proportion done should be agreed with the contractor. Sometimes all but a minor aspect of an item is completed, for example, final painting of valves in a valve chamber.
It is simpler to certify the item in full rather than making some trivial reduction, making a note to remind the contractor if he fails to complete the painting.
If work has been done so badly that it cannot be accepted, no payment should be certified for it. If the contractor has agreed to do some remedial work that will make it satisfactory, some partial payment can be made. All depends on the circumstances. With a reputable contractor and a responsible agent there is no reason to assume that verbal promises will not be carried out. With good contractors most agreements are verbal anyway, and any paperwork is only for the purposes of record.
Some agents leave the contractors quantity surveyors to prepare the contractors accounts. When the quantity surveyors are approached and asked not to repeat in every account items of claim previously struck out as being invalid, they may reply they have no authority to remove an item once it has been put into an account. Continued practice of this kind means that, as the measurement gets larger, the resident engineer may have to make an increasing number of corrections to items, page totals, and bill summaries. If the engineer is unable to get the practice altered if necessary by direct approach to the contractors senior personnel it at least eases the problem to insist, from the beginning, that all extras, added items and claims are billed on a separate sheet, or added at the end of each bill.

Scroll to Top