In the construction of a two-span bridge (span length = L) by using span-by-span construction, why is a length of about 1.25L bridge segment is constructed in the first phase of construction?

Basically, there are mainly three reasons for this arrangement: (i) The permanent structure is a statically indeterminate structure. During construction

In the construction of a two-span bridge (span length = L) by using span-by-span construction, why is a length of about 1.25L bridge segment is constructed in the first phase of construction? Read Post »

In designing concrete structures, normally maximum aggregate sizes are adopted with ranges from 10mm to 20mm. Does an increase of maximum aggregate size benefit the structures?

Basically, the force supplied by a concrete compression machine is a definite value. For normal concrete strength application, say below

In designing concrete structures, normally maximum aggregate sizes are adopted with ranges from 10mm to 20mm. Does an increase of maximum aggregate size benefit the structures? Read Post »